Acciaierie d'Italia (ADI) has halted operations in the hot area of its Taranto steel plant, according to Energia Oltre. The shutdown procedures for the blast furnaces started in early November, after Italy's Court of Cassation rejected appeals filed by Ilva and Acciaierie d'Italia. The halt coincides with a setback on decarbonization funding.
Around EUR1 billion had originally been allocated to a direct reduced iron (DRI) plant serving the former Ilva site, and later to broader decarbonization measures in the steel sector at Taranto. In June 2026, the government moved the funds from the budget of the Ministry of Environment and Energy Security to the Ministry of Enterprises and Made in Italy, citing a lack of resources. At the same time, the requirement to use the money for the Taranto DRI plant and DRI d'Italia was dropped, and the funds were redirected toward general support for the steel industry's green transition.
The draft budget law for 2027-2029 ultimately canceled the EUR720.6 million allocation planned for 2027-2030, which had been intended for environmental upgrades and electric arc furnace construction in Taranto. Following the court rulings, ADI has shifted its focus to rolling services at the Taranto plant, according to Argus Media. Because the plant's own steelmaking and slab production capabilities are limited, the company must rely on imported semi-finished products.
It has therefore offered spare rolling capacity to third-party customers in the second half of the year. Market participants indicated that the tolling fee quoted by the company, at EUR160-170 per tonne, is economically unjustified under current conditions, except possibly for the largest buyers able to benefit from large slab volumes or better individual contract terms. According to sources, plate production lines were not part of the tolling service discussions.
On November 9, binding bids for the former Ilva steel plant were submitted by India's Jindal and Italy's Arvedi Group, Reuters reported, citing the extraordinary commissioners. The bids will be assessed for compliance with the tender terms. Financially, Acciaierie d'Italia ended the first half of 2026 with a loss of EUR551.5 million.
Its debt to suppliers reached EUR1.75 billion, while total debt stood at EUR8.5 billion. Sources: Energia Oltre, Argus Media, Reuters, as reported by IndexBox (indexbox.io).
Source: indexbox.io