Capstone Copper (TSX: CS; ASX: CSC) has lowered the bottom of its annual copper production forecast by 5,000 tonnes after delaying the full restart of its Pinto Valley operation in Arizona until mid-December, according to The Northern Miner. The revised production floor is 195,000 tonnes, below the bottom of the 200,000-to-230,000-tonne range the company forecast in its October 29 results, when it had also expected cash costs at the upper end of guidance. In an update released on Thursday, the company said the primary crusher needs additional repairs to major mechanical components being manufactured off-site by the original equipment maker.
Mobile crushers should allow partial processing to resume in mid-November. According to the company's estimate, the additional downtime would reduce this year's copper output by about 5,000 tonnes, depending on restart timing. The temporary mobile crushers could support throughput of up to 40,000 tonnes per day during the interim restart, about two-thirds of the nominal milling capacity of the open-pit operation, which is about 130 km east of Phoenix and has a 60,000-tonne-per-day concentrator.
Jefferies mining analyst Tariq Fahad described the 5,000-tonne impact as “modest” but said it “adds to a difficult operational year at Pinto Valley and [the company's] Mantoverde” operation in Chile. “In our view, the bigger concern is execution, with investors likely looking for improved operating reliability into 2027,” he said in a note on Thursday. Capstone shares fell 4.5% to C$10.26 late on Friday morning in Toronto, extending Thursday's 6.5% decline. According to The Northern Miner, the company's market capitalization stands at about $7.9 billion (US$5.6 billion).
Capstone is also dealing with the effects of a national strike in Chile, called by Chilean trucking groups and a civic movement to protest high fuel prices. The company said the stoppage threatens concentrate and cathode shipments as well as deliveries of fuel and sulphuric acid. Preventive measures and on-site storage have so far protected output at Capstone's two Chilean operations.
TD Securities mining analyst Craig Hutchison said that, together with the Pinto Valley delays, the strike introduces “incremental downside risk to year-end production.” National Bank Financial mining analyst Shane Nagle cut his rating on Capstone to sector perform from outperform, citing “near-term operational uncertainty.” He said consistent operational performance at Mantoverde and Pinto Valley will be important to supporting a re-rating that has been materially affected by Thursday's release. Pinto Valley produced 6,358 tonnes of copper in the third quarter, compared with 9,949 tonnes a year earlier, while its nine-month output was 27,115 tonnes, down from 30,960 tonnes, as Capstone reported in October. The plant restarted with mobile crushers on October 1, before commissioning of the primary crusher began on October 21, when additional repairs were identified.
Group output totalled 45,218 tonnes in the third quarter, down 18% from a year earlier. To lift fourth-quarter production, Capstone was counting on higher grades at Mantoverde and Mantos Blancos, as well as completion of the Mantoverde concentrator expansion tie-in. In September, the company agreed to sell its Cozamin mine in Mexico to Luca Mining (TSXV: LUCA) for up to $385 million (C$549 million).
Closing was expected in the fourth quarter, subject to conditions and approvals, Capstone said in October. Capstone's annual production target includes a full year of Cozamin output. Source: The Northern Miner (Frederic Tomesco, November 13, 2026), citing Capstone Copper's operational update, analyst notes from Jefferies, TD Securities and National Bank Financial, and Capstone's October reporting.